I love the term falsework... wonder if I can get me some of that...
- Concrete was placed for new Dock 5 bents 1 - 5. The Contractor will be stripping the forms this week and starting on the falsework construction for bents 6 - 10. Utility support hangers will also be installed beneath new bents 1 - 5. Also, the mechanical and electrical subcontractors will start installing their piping beneath new bents 1 - 5.
- Old Dock 6 demolition continues. Demolition debris is being processed at the Contractor's laydown area along the West Wall.
- Old Dock 5 select demolition continues.
Contact Personnel:
Port of Seattle Resident Engineer Chris Sherwood 728-3310
Sr. Inspector Ken Sanberg 571-0127
Project Manager Tim Leonard 728-3018