Pile driving is complete for new Dock 5 fixed pier. Rebar installation and formwork continues for the new pile caps on Bents 1 - 5. Concrete placement is scheduled to take place mid-week.

ยท Old Dock 6 demolition continues. Demolition debris is being processed at the Contractor's laydown area along the West Wall.

Contact Personnel:

Port of Seattle Resident Engineer Chris Sherwood 728-3310

Sr. Inspector Ken Sanberg 571-0127

Project Manager Tim Leonard 728-3018

Comments

No Comments

This Blog

Syndication

Recent Posts

Tags

News

Add to Technorati Favorites <!--SBM--> <SCRIPT LANGUAGE="JavaScript"> function mOvr(src){src.className="sbmDark"} function mOut(src){src.className="sbmDim"} </SCRIPT> <!--SBM-->

Clubs I've Joined

Useful Web Sites

People Out There Cruising

Blogs I Read

Magazines I read

Archives

CommunityServer 2007.1 (Build: 20917.1142)
Aero 2007 SP2.2 (Build: 2007.6.28.32271)
Dream Armada, LLC, Copyright 2005