Things seem to be clicking along down at Fisherman's Terminal.
- The Contractor has turned over new Dock 6 to the Port of Seattle. Grout was placed for the new knuckle-boom crane, allowing the crane to be set and tested. Testing is scheduled to take place later in the week by a certified independent crane inspection company.
- Pile driving is complete for new Dock 5 fixed pier. The welding crew continues to weld structural rebar into the steel piles. A crew is installing false work & formwork for the new pile caps.
- Old Dock 6 demolition is scheduled to continue this week.
Contact Personnel:
Port of Seattle Resident Engineer Chris Sherwood 728-3310
Sr. Inspector Ken Sanberg 571-0127
Project Manager Tim Leonard 728-3018