Note the point about Bike Lockers. If you're interested there are only 6 lockers remaining....
The Marina Office will be closed On Monday January 21st
X-DOCK CLOSURE
- Monday, January 21st through Friday, January 25th For installation of two "wing" floats
- No launching onto or from X-dock using the 3-ton and 5-ton hoists.
- Boats may be launched using the 3-ton hoist and W-dock north of Corinthian Yacht Club
The contractor's lay down area for Phase III of dock installation is in the parking lot just east of the old N, O & P docks. The sidewalk and fire lane will be closed when floats are transferred from trucks to the water. The contractor will remain in this area until end of February 2008.
Bike storage lockers and bike racks have been installed throughout the marina. There are only 6 bike lockers remaining to be rented. Contact the Marina Office if you would like to store your bike out of the weather this winter.
Phase III Dock Schedule:
- New P dock to be completed February 1, 2008 - 36 foot slips
- New Q dock to be completed February 22, 2008 - 34 and 36 foot slips
Marina Office Hours: Monday - Saturday 8:00 AM to 4:30 PM
Questions? Call the Marina Office at 206-728-3006